TL;DR: Before starting on a migration, ensure that you've answered the following questions:
- Have you identified the key risk factors to reaching 100%?
- How can you structure the migration to “fail fast” on those key risks (and preserve full rollback)?
- Does value require reaching 100%, or can you define incremental landing points?
- How will you handle the operational grind?
- Is your project actually a migration, or is it a “both-and”?
- Have you fully leveraged AI to de-risk the hard parts up front?
Overview
To avoid Chromium ossifying, we periodically need to undertake large cross-platform migrations from an existing subsystem to a new one.
However, because Chromium supports so many products and platforms, maintains a high bar for relative performance and correctness during transitions, and sees team priorities shift over long timelines, migrations frequently end up unfinished. We then end up supporting both the old way and the new way in production indefinitely. This carries a high ongoing cost for maintenance, robustness, and flexibility, especially as partial migrations interact in a combinatorial explosion of flows and can leave Chromium worse off than before the migration started.
This doc offers guidance based on our collective experience undertaking migrations in Chromium (often learned the hard way, since many of these dynamics are only obvious in hindsight!). It is framed as a set of questions to ask yourself at the start of a migration to give your effort the best chance of success and to avoid leaving Chromium indefinitely supporting two competing systems.
What Do We Mean by a “Migration”?
In this doc, a migration means transitioning Chromium from an existing subsystem that provides some functionality (e.g., metrics collection) to a new subsystem (supporting either the existing API surface or a new one), where carrying both the old way and the new way implies non-trivial extra maintenance and/or cognitive load, and where the migration is finished only when the old subsystem is no longer in use and deleted.
(Note: Incremental codebase-wide style or idiom improvements, such as “prefer std::views when touching code”, do not carry that dual-subsystem burden and aren't the focus of this guide; see the rubric for guidance on those changes.)
Questions to Ask at the Start of Your Migration
1. Have you identified the key risk factors to reaching 100%?
In our experience, two obstacles account for many of the cases where a migration gets blocked from reaching 100% and deleting the old code:
- A platform or legacy use case that simply can't be ported: For example, an obscure platform constraint or legacy client (or external callers relying on undocumented side effects or event ordering) that fundamentally doesn't fit the new model, only discovered deep into execution.
- “Code-complete, stuck in Finch forever”: Getting the code landed behind a flag (or launched on easy platforms), only to spend years unable to launch to 100% and delete the old code path due to performance, memory, or correctness regressions on the most constrained platforms or flows.
Before starting, put in the cycles up front to audit all platforms and callers for unportable edge cases, and identify which platforms or flows will be the hardest for meeting Chromium‘s performance, memory, and stability bar at 100% Finch rollout. Where the old subsystem is selected or fallen back to at runtime (e.g., a legacy backend or persisted format where code search alone cannot show what still uses it in the wild), add localized telemetry at the legacy subsystem’s entry point up front so you can see which configurations actually hit it (and later verify usage has reached 0% before removing it).
2. How can you structure the migration to “fail fast” on those key risks (and preserve full rollback)?
When building a new feature, a natural instinct is to build and launch on the simplest client or platform first to show momentum. In a migration, doing the easiest targets first commits us to supporting the new way in production before we know whether the hardest cases in Question 1 are solvable.
Instead, structure the migration to fail fast:
- Prove out (and benchmark in production) the hardest platforms, clients, or performance-sensitive flows first, so that you can bail out cleanly if those risks prove insurmountable.
- Preserve the ability to do a full rollback to the old way until you are confident the new way can launch to 100% (or until you have reached a defined incremental landing point; see Question 3). In general, runtime feature flags (per Chromium's Flag Guarding Guidelines) should be the baseline mechanism for preserving rollback, especially as shorter release cycles leave less pre-Stable soak time to shake out regressions. Additionally, ensure that you design persisted state for safe rollback up front and trace what happens if a user rolls back after hitting the new format - aim to avoid data loss, corruption, or subtle state divergences.
3. Does value require reaching 100%, or can you define incremental landing points?
Many migrations are designed as “all-or-nothing”, where the real benefits only materialize at 100% when the old subsystem is finally deleted. In a multi-quarter effort, team priorities or staffing can shift halfway through; if the migration is all-or-nothing, stopping early leaves Chromium strictly worse off by carrying the permanent burden of two systems in production.
Ask up front:
- Is your migration dependent on reaching 100% to unlock its key benefits? (If so, preserving rollback per Question 2 is especially critical.)
- If not, how can you structure the migration into phases with incremental landing points, where if you have to stop after Phase 1, real benefits have already been locked in and the ongoing complexity of coexistence is low and bounded?
- Can you define concrete metrics (often domain-specific, such as incoming bug rate or crash class frequency) to illustrate the problem or complexity you are aiming to reduce, and to measure both progress toward completion and the value delivered at each stage?
4. How will you handle the operational grind?
Even when a migration is technically proven, the standard 80/20 rule applies: completing the first 80% of the migration often takes 20% of the time, while the final 20% takes 80% of the time. To avoid stalling out in the long tail, make sure your plan addresses four operational questions:
- How and when will you turn off the tap on the old way? Without early guardrails (such as presubmits,
DEPS, or visibility restrictions), other engineers across Chromium will keep adding new callers or features to the old subsystem while you are migrating existing ones. - Who will actually write the long-tail CLs? Expecting dozens of client teams with their own priorities to migrate their own working code rarely succeeds. Plan and staff for the migrating team to drive the caller migrations directly, only needing client owners for review. For Googlers (or Googlers assisting in migrations driven by external contributors), you must ensure that the migration follows go/chrome-churn-policy. For non-Googlers looking to drive external migrations without a Googler partner, you should be in touch with Chrome ATLs while early in the proposal phase. Note that once the upfront risks are retired (see Question 6), you can and should lean into AI coding tools to accelerate progress on fanout (while abiding by Chromium's AI coding policy).
- How will you handle other projects concurrently touching the same codepaths? It can arise that concurrent projects need to operate on the same shared surfaces, which can increase complexity and require cross-team sequencing and coordination. Try to identify engineers/teams with whom you should stay in contact during the migration to identify and mitigate this risk.
- How will you handle the cost of supporting both ways while the migration is in progress? Account for the ongoing cost of testing, monitoring, and debugging both the old and new subsystems in production for the duration of the migration.
5. Is your project actually a migration, or is it a “both-and”?
There are valid use cases for transitioning some platforms or clients to a new way of doing <X> while others remain on the old way. A common example is a new code path or architecture that could in principle be supported across all platforms, but brings a compelling benefit only to one platform (meaning that porting the remaining platforms would be a long tail of work that is unlikely to actually be prioritized).
Be internally clear at the start about whether your realistic goal is removing the old way everywhere (a migration) or selectively adding a new way alongside the old way (a “both-and”). If it is a “both-and”, your proposal should:
- Make it explicit that you are not proposing to remove the old way.
- Define the exact target configurations for the new way.
- Explicitly weigh the benefit of having those targets on the new way against the permanent cost of supporting both ways indefinitely.
6. Have you fully leveraged AI to de-risk the hard parts up front?
AI has the potential to impact the questions above both negatively and positively. AI agents can make it tempting to immediately convert the easiest 80% of mechanical call sites and land a bunch of CLs on main. In a migration, doing the easiest parts even faster just locks Chromium into a dual-system state faster without retiring any of the real risks in Questions 1-4 (note that once those risks are retired, AI is a great fit for driving the fanout in Question 4).
Ask how you can use AI before deep resource investment or landing commitments on main:
- Can you use AI up front to audit all existing callers and surface “unportable” legacy edge cases?
- Can you use AI to prototype a rough conversion of the hardest or most performance-sensitive target (or even a 100% conversion) on a branch, so that you can test and benchmark it before committing on main?